Underpass work set to begin at Eklingpura Chauraha


Underpass work set to begin at Eklingpura Chauraha

UIT is gearing up for construction of the underpass at Eklingpura chauraha. It is expected that the underpass construction will be completed in one year's time frame.

 

Underpass work set to begin at Eklingpura Chauraha

UIT is gearing up for construction of the underpass at Eklingpura chauraha. It is expected that the underpass construction will be completed in one year’s time frame.

To ensure smooth progress of the construction work, UIT has initiated work on shifting the 11KV and LT electricity lines that are coming along the route. These 2 electricity lines will have to be completely shifted before work can commence on this.

Tendering process for shifting has been initiated. Tenders will be opened on 26-May and work orders will then be released. Contractors will be given 3 months for shifting the lines. This work is estimated to cost Rs 99.5 Lakhs.

Tendering process for construction of underpass has also begun. The construction is expected to cost Rs 7.52 Cr with a target of completion within one year.