Road Work at Fatehpura Circle Delayed


Road Work at Fatehpura Circle Delayed

Commuters facing inconvenience as road work remains incomplete causing traffic jams
 
Fatehpura circle

Udaipur, December 4,2024 - The delay in completing the road work at Fatehpura Circle, one of Udaipur’s busiest intersections, is causing significant trouble for commuters. Despite the removal of a bottleneck over a month ago, the road remains incomplete.

Shops Demolished to Remove Bottleneck

As part of the project, eight shops on the Bedla-to-RK Circle route were demolished by the UIT on November 3, 2024. The removal aimed to ease traffic congestion at this busy intersection.

Temporary Road Created

After clearing debris, UIT laid a temporary gravel road. However, proper blacktopping has not yet been completed, making travel difficult for vehicles. The intersection connects key routes, including Mount Abu, Nathdwara, Jaipur, and Sirohi, with approximately 66,000 vehicles passing through daily.

Pipeline Repairs Cause Delays

UIT officials explained that several pipelines were damaged during the demolition process, which caused delays. The repairs are now complete, and UIT expects to finish the road construction within the next 15–20 days.

Similar Work Completed Faster Last Year

Previously, another bottleneck was removed on the opposite side of Fatehpura Circle, at the turn from RK Circle to Sukhadia Circle. The clearance began on September 26 last year, and by December 5, all obstacles were removed. The road construction started on December 14, 2023 and was completed within 10 days, including proper blacktopping.

Source: Media Reports