As per reports in the media, certain State Government Housing schemes in the Rajsamand District have yet too see the light of the day.

The report mentions that construction of 288 flats under the Chief Ministers Housing Scheme (Mukhya Mantri Awaas Yojna) is yet to be completed. The Rajsamand Municipal Council reportedly has served the notice to the construction firm when the  work was supposed to be completed in October 2022. However, of the 1072 flats, only 135 have supposedly been handed over to the beneficiaries and only 10-15 people are staying in these flats. The general services and facilities are yet not complete.

Rajsamand News Housing Flats Delayed

The construction work, which has been ceased over the last many months has just begun while the utilities in the completed flats are yet not fully functional. As per the agreement, 288 flats out of 1072 in the mentioned scheme operational behind the Devthadi Police Lines were supposed to be handed over by October 2022.  The Rajsamand Municipal Council has reportedly served notice to the contractor twice since. As per  the information available, the contract was awarded to National Consumer Cooperative Federation. The work was sub-contracted  to another  firm. As per  the  agreement, the work was supposed to get over in February 2021, but due to the COVID pandemic, work was delayed. This resulted in the official hand over date for the 288 flats to be extended to 31 October 2022.

The story, reported in Rajasthan Patrika mentions the following facts related to the housing scheme:

  • 1072 flats were supposed to be constructed.
  • 464 flats under LIG have been completed.
  • 352 flats under EWS have been completed.
  • 288 flats yet to be completed.
  • 135 possessions given.
  • CC Road to reach these buildings is not yet completed.
  • Utilities not fully functional.
  • Aanganwadi, Community Centre, Green Area, STP yet to be completed.
  • Water  only available  through Boring...Govt Pipeline yet not established.

Tarun  Baheti, the  XEN of the  Rajsamans Municipal Council told the newspaper the work under the scheme has restarted a few days back and tenders for construction of the  roads and STP are also in process.

Source: Rajasthan Patrika