Rajasthan's 6000 MWh BESS Projects Reviewed

Energy Minister directs completion of all BESS projects between December 2026 and November 2027

 | 
Energy

UdaipurTimes, Nov 24, 2026 - Energy Minister Hiralal Nagar on Monday (November 23) chaired a high-level meeting at Vidyut Bhawan in Jaipur to review the progress of 6000 MWh Battery Energy Storage System (BESS) projects being established across Rajasthan. The meeting was attended by Energy Department officials, Rajasthan Rajya Vidyut Utpadan Nigam and selected BESS developers appointed through NTPC Vidyut Vyapar Nigam.

During the meeting, the progress of various BESS projects was reviewed in detail, with discussions covering project timelines, construction activities, land availability, grid connectivity and necessary approvals.

The Energy Minister said the State Government is making concerted efforts to achieve energy self-reliance and strengthen the State's power system through modern energy storage technologies, ensuring a more robust and reliable electricity supply.

The Minister specifically directed JSW to complete its 250 MWh battery storage projects at Giral and Suratgarh by December 2026. Officials of the State power generation corporation were also instructed to closely monitor all ongoing BESS projects to ensure their benefits become available to Rajasthan on time.

Directors and representatives of several BESS developer companies attended the meeting.

The scheduled completion period for these projects ranges from December 29, 2026, to November 7, 2027. The meeting also focused on resolving implementation challenges, improving coordination among stakeholders and accelerating construction activities.

The Energy Minister firmly warned all BESS developers that failure to complete projects within the stipulated timelines would invite strict action. He assured developers that the State Government would extend the necessary support and coordination to resolve issues affecting project implementation.

Highlighting the importance of BESS projects, Nagar said they would play a crucial role in integrating renewable energy into the State's power network, maintaining grid stability and ensuring a reliable electricity supply. He added that work orders had been issued in phases to meet the targets set by the Central Government under the Viability Gap Funding (VGF) scheme.

The work orders cover the following capacities:

  • State Component: 1,000 MWh (2-hour, 2-cycle system).
  • Central Component: 1,000 MWh (2-hour, 2-cycle system).
  • PSDF Scheme: 2,000 MWh (2-hour, 2-cycle system) and 2,000 MWh (4-hour, 1-cycle system).

Rajasthan secured some of the lowest tariffs in the country at the time, ranging from Rs 1.77 lakh to Rs 2.85 lakh per MW per month for these projects.

Once operational, the projects are expected to improve grid stability and help provide affordable electricity to the State during peak demand periods.